Proposition 45: What Public Agencies Need to Know
October 6, 2026California voters will decide this November whether to approve Proposition 45, a 41-page ballot measure sponsored by the California Chamber of Commerce that would make sweeping changes to the California Environmental Quality Act and other state laws governing environmental review and project permitting. The measure would alter how agencies evaluate projects’ environmental impacts, compress agency review timelines, create new litigation exposure for public agencies, and limit judicial remedies when violations of law occur.
This article summarizes the aspects of Prop 45 most likely to affect cities, counties, special districts, and other public agencies.
Covered Projects
Prop 45 would apply to a broad range of projects across multiple sectors. These include data centers, freeway expansions, dams, warehouses, forest clear-cutting, dairy biogas and landfill gas facilities, CO2 pipelines, large-scale sprawl housing developments in high wildfire-risk areas, and numerous others. Unlike prior streamlining measures such as SB 7 or SB 149, the measure does not require the Governor or any state agency to certify that a project qualifies for coverage. Instead, eligibility disputes will be resolved by courts, and the initiative instructs courts to interpret its provisions to “afford the fullest possible weight to the interest of, and the approval and realization of” covered projects.
Changes to Environmental Review Standards
Two provisions would fundamentally alter how agencies determine whether a project’s environmental impacts are significant.
First, a project’s significant impacts would be determined “solely upon” compliance with “existing laws,” defined as any statutes, regulations, rules, standards, or ordinances in effect when the application was filed. Under current law, lead agencies select the applicable thresholds of significance, which must reflect current scientific evidence and may be updated as new information becomes available. The measure would lock in whatever standards exist at the time of project application, regardless of whether those standards actually address the harms a project may cause.
Second, project applicants would gain the right to “vest into” any thresholds an agency has previously published, adopted, or routinely used, and the agency cannot override that election. Agencies that have not codified comprehensive significance thresholds across all project categories may find themselves without adequate standards for evaluating large, complex projects. This is a particular concern for smaller jurisdictions with limited planning staff.
Restrictions on Alternatives Analysis
Currently, agencies must evaluate a “reasonable range” of feasible alternatives designed to reduce a project’s significant environmental impacts. The measure would sharply curtail that requirement. Through a new process that the measure creates, a project applicant can designate a single alternative to the proposed project. When that happens, the measure would prohibit agencies from considering any other alternatives. It also would prohibit agencies from considering alternative project locations. For responsible agencies, such as cities, fire districts, or water districts that issue permits for projects where another jurisdiction acts as the lead agency, a project’s location can significantly affect the cost of providing services like fire response, water supply, and road access. Under Prop 45, responsible agencies would be barred from proposing a different site that could substantially lower those costs.
New Developer Right of Action
Under current law, project applicants generally cannot sue public agencies when they deny projects because the California Environmental Quality Act does not apply to projects that an agency rejects. Prop 45 changes the law by creating a new right of action for project applicants to sue agencies for project “denial[s] or imposition of unlawful conditions of approval.”
For project types covered by the measure, Prop 45 could double an agency’s litigation exposure. Projects can already be challenged if an agency approves a project with inadequate environmental review. In those cases, however, the project applicant often indemnifies the public agency and covers any litigation costs. Under Prop 45, a project applicant could sue the agency for denying a project or imposing conditions of approval on a project that the applicant does not like. The conditions of approval that applicants could challenge often include mitigation measures that protect communities from project-related harm. It is also worth noting that if a project developer were to sue a public agency under this new right of action, the agency could not rely on the indemnification protections that they often secure from developers to cover litigation costs.
Compressed Timelines
Several of the measure’s timeline provisions would require agencies to change how they operate.
Comment periods. Under current law, public comment periods on environmental documents are minimums – for example, at least 30 days for a draft EIR, or 45 days when state agency review is required – and agencies have discretion to extend them if necessary. Prop 45 would convert these minimums into maximums and provides that they “shall not be tolled or extended except by a court of competent jurisdiction.” An agency that needs additional time to review could not stipulate to an extension with the project applicant, for example. Any extensions would require a court order, which means that, in practice, they would rarely occur.
Application review. The measure would extend the Permit Streamlining Act’s 30-day completeness determination deadline to all covered projects, including large infrastructure developments involving general plan amendments or zone changes that are currently exempt from the PSA’s expedited timelines.
Responsible agencies. The measure requires responsible agencies to issue a final decision before the later of 90 days from application completeness or one day after the lead agency approves the project. For agencies whose governing procedures require advance public notice and a noticed hearing – for example, local water districts or cities acting as responsible agencies and subject to the Brown Act – the one-day trigger is potentially unworkable. These agencies would likely need to negotiate deadline extensions from project applicants, who have no legal obligation to agree.
Weakened Judicial Remedies
If an agency wishes to challenge a project’s environmental review in court, the measure would significantly limit the relief courts could provide. Courts would be able to issue temporary injunctions while the litigation is pending only upon finding “clear and convincing evidence” that the project would have a “specific, adverse impact upon public safety,” a significantly narrower standard than current law. Under current law, courts consider the likelihood the petitioner will prevail on the merits and the relative balance of harms to public interests that are likely to result from the issuance or non-issuance of the injunction. Further, courts are not currently limited to injunctions that address only impacts to public safety; they may consider harm to public health and the natural environment.
Courts also would not be able to rescind project approvals. As a result, agencies that sue to prevent a project from harming public health or the environment could find that victory provides little, if any, meaningful relief.
Legal Uncertainty, Cost, and Amendment Difficulty
By overhauling core provisions of the California Environmental Quality Act and unsettling five decades of established case law, Prop 45 could generate years of costly litigation as courts interpret the measure’s scope and new terms. Agencies would likely need to commit significant staff and legal resources to develop new regulations, update procedures, and defend their interpretations when challenged.
The Legislative Analyst’s Office estimates that simply implementing Prop 45 could cost local and state governments more than $100 million annually. In addition, the measure’s rollback of public health and environmental protections would allow project applicants to shift the cost of mitigating project impacts onto public agencies and taxpayers. When environmental impacts go unidentified and unmitigated, agencies and their constituents often bear the costs. For example, Californians are already spending more than $750 million to clean up lead contamination from just one industrial facility in Southern California, a project that operated for decades before the California Environmental Quality Act was in place.
Further, Prop 45 could be changed only by a vote of the people or by a two-thirds vote of the Legislature. Critically, any amendment by the Legislature must “further[] the purposes” of the measure. Accordingly, the Legislature would have limited ability to correct problematic provisions if the measure passes.
Looking Ahead
Proposition 45 would represent the most significant change to the California Environmental Quality Act since the statute’s adoption in 1970. Public agencies should consider the potential operational, fiscal, and legal implications as part of their planning for the November election and beyond. The full text of the initiative and the LAO’s fiscal analysis are available through the Secretary of State’s website.